Construction progress

Construction log

Updated monthly — with photos from the site. Status as of September 2026.

Building A

handover Q4 2027

Shell completed

Building B

handover Q2 2028

Foundations completed

Building C

handover Q2 2028

Excavation

  1. September 2026

    Building A

    Shell completed

    The structure of all six storeys of Building A is complete. Next up: the roof and window installation.

  2. July 2026

    Building B

    Foundations completed

    The foundation slab and the walls of the underground garage below Building B are ready. Work on the ground floor structure begins.

  3. June 2026

    Building C

    Excavation begins

    Work on the Building C plot has started. Excavation for the underground garage will last until the end of summer.

Want to see the construction up close?

Our sales office is on site — we will show you the construction from a safe vantage point.

Cookie settings

You can change your consent at any time — the “Cookie settings” link is in the footer.
Strictly necessary Your cookie settings and the site’s security. Always on.
Always
Google Analytics — number of visits, most read pages and where visitors come from. Cookies _ga and _ga_*, 2 years.
Details: Privacy policy